This Shell & Core and partial Cat A fitout achieved LEED & Wired Score Platinum as well as an A3 BER rating. This building was constructed in the front garden of the original Cumberland building using Revit/BIM and had an M&E value in excess of €6m.
Due to the footprint constraints the main plantroom was installed in the -2 basement. This provided a unique challenge to achieve the clients requirements of a LEED & Wired Score platinum building with a an A BER rating.
The project achieved LEED platinum, wired score platinum & a A3 BER rating. This was achieved due to the close working partnership of the design team.
A detailed design & co-ordination package was put together to ensure the proposed design would work correctly by working closely with the design team & then the construction team. All plant had to be installed early in the project in the basement which provided a difficult challenge during construction.
PM Lafferty's
QS KSN Construction Consultants
MCA Architects
Cora
Flynn
Jones Engineering