This mission-critical facility involved the relocation of the Aer Lingus Operations Control Centre from Hangar 6 (Airside) to Shamrock House (Landside) within the Dublin Airport campus. The Operations Control Centre is a 24-Hour, 7-day operation, and the Works involved the installation of a new Generator to ensure continuity of supply. The conclusion of the Works involved a managed handover between both facilities without any downtime.
Designing M&E Services for a mission-critical facility with minimum allowable downtime.
Micro-managed programme/scheduling ensured seamless transition from old Control Centre to new on a scheduled weekend.
Comprehensive TV & Comms Installation, delivering 1 GB capability. Primary Electrical Services throughout Control Centre and VRF Fan Coil system. Circadian-rhythm control of lighting throughout.
Turner Townsend Project Managers & Quantity Surveyors
Douglas Wallace Architects
Europlan Services Structural Engineers
BB7 Fire